Progress:
The work of building excess road, supporting wall, gate and ground leveling are finished. The water tank has been already built. The deep well water supply is complete. The main building has been built up to the 2nd half floor where the proposed 4 big rooms on the ground floor and the 4 rooms on the 2nd floor,2 kitchen on the 3rd floor and 2 bathrooms on the first floor have been built.
The remaining work includes: Constructing the 3rd & 4th floors; fixing the windows and doors; constructing the kitchens and bathrooms; finishing the water and electric supplies; painting and generally finishing all the building works.